The Job:
Lift and relay / provide and lay PCC flags in the footpath of Kings Road. Installation of new concrete driveways.
This project involved the lifting and relaying of a PCC footpath and the construction of new concrete driveways (100mm Type 1 MOT and 150mm of C40 fibre-mesh concrete) on Kings Rd. The footpath and driveways had been damaged over the last 30 years by tree roots and vehicle override. Following the successful construction of the new footpath and new concrete driveways early in the scheme, WBC increased the scope of the works to include additional properties on Kings Road.